PMI Scheduling Professional Certification (PMI-SP) Practice Exam

Disable ads (and more) with a membership for a one time $4.99 payment

Prepare for the PMI Scheduling Professional Certification Exam with flashcards and multiple-choice questions. Each question comes with hints and explanations. Get ready for your certification!

Practice this question and more.


What does "fast-tracking" a schedule involve?

  1. Changing project managers during the project

  2. Overlapping critical activities rather than executing them in sequence

  3. Reducing the project budget

  4. Increasing the timeline for project completion

The correct answer is: Overlapping critical activities rather than executing them in sequence

Fast-tracking a schedule involves overlapping critical activities rather than executing them in sequence. This technique is used to expedite the project timeline by allowing simultaneous execution of tasks that would typically occur one after the other. By identifying activities that can be overlapped, project managers aim to shorten the duration of the project without changing the original scope. This often requires careful analysis to ensure that overlapping tasks do not adversely affect the project's quality or increase the likelihood of risks. The effectiveness of fast-tracking lies in its ability to compress the schedule while still achieving deliverables on time. It is essential, however, for project teams to closely monitor the progress of overlapping activities to ensure that dependencies are managed effectively and that potential conflicts are resolved promptly.