What is PV in the context of project management?

  1. The planned value assigned to project work

  2. The perceived value of outcomes

  3. The profit value for project stakeholders

  4. The present value of cash flows

The correct answer is: The planned value assigned to project work

In the context of project management, Planned Value (PV) is defined as the estimated value of the work that was planned to be completed by a certain time in the project timeline. It serves as a fundamental metric in project performance measurement, particularly within the framework of earned value management (EVM). PV is derived from the project's budget and schedule, representing the value of work that should have been accomplished at a specific point in time according to the project plan. It helps project managers assess whether the project is on track, behind, or ahead of schedule by comparing it to actual performance metrics. Understanding PV is crucial for effective project management because it assists in performance monitoring and forecasting project completion. By measuring the actual work completed against the planned value, project managers can make informed decisions regarding resource allocation, schedule adjustments, and budget management.