PMI Scheduling Professional Certification (PMI-SP) Practice Exam

Disable ads (and more) with a membership for a one time $4.99 payment

Prepare for the PMI Scheduling Professional Certification Exam with flashcards and multiple-choice questions. Each question comes with hints and explanations. Get ready for your certification!

Practice this question and more.


Which of the following is NOT an input for the Control Team process?

  1. Work performance data

  2. Project documents

  3. Change requests

  4. Agreements

The correct answer is: Change requests

The correct response regarding which option is NOT an input for the Control Team process is change requests. In project management, particularly in the context of controlling aspects of team performance, the inputs typically include work performance data, project documents, and agreements, all of which provide essential information for evaluating and managing the project’s performance. Work performance data consists of the raw observations and measurements that result from activities being performed to carry out the project work. This data is vital for assessing current performance against the project plan. Project documents may include schedules, performance metrics, and status reports, which all help in tracking progress and managing the team's performance effectively. Agreements represent contractual obligations and understandings that guide project execution and control. Change requests, while critical in project processes, specifically pertain to the procedures for managing changes to the project's scope, schedule, or costs. They are not considered an input to the Control Team process itself but rather a mechanism that is utilized when adjustments or changes are necessary as a result of the control process. Thus, in the context of this specific question about the Control Team process, change requests are not among the inputs required.